FixUp Experts
Project Timeline

How Long Does a Kitchen Remodel Take in Houston?

Day-by-day breakdown of a typical kitchen remodel in The Woodlands area — what happens each phase, what speeds it up, what slows it down.

📅 April 23, 2026 ⏱ 6 min read ✍️ Nick Alekseev, Owner

The honest answer

Most kitchens in The Woodlands take 3 to 6 weeks from demo to final walkthrough. The factor that varies most: countertop fabrication time (10-14 days from template to install) — this is the single biggest schedule driver.

Timeline by project type

  • Refresh (paint, hardware, fixtures): 4–7 days
  • Cabinet refacing: 1–2 weeks
  • Mid-range remodel (new cabinets, counters, tile): 3–4 weeks
  • Full gut remodel (layout changes, custom cabinets): 5–7 weeks
  • Luxury custom (premium materials, structural): 8–12 weeks

The 7 phases of a kitchen remodel

  1. Planning & ordering (1–4 weeks before construction) — Final design, cabinet/material orders, permits.
  2. Demo (1–3 days) — Remove old cabinets, countertops, flooring, fixtures.
  3. Rough-in (3–7 days) — Plumbing, electrical, HVAC adjustments.
  4. Drywall & paint prep (3–5 days) — Patch, texture, prime, base coats.
  5. Cabinet install (2–4 days) — Set boxes, level, secure.
  6. Countertop template & install (~2 weeks: template → fabrication → install).
  7. Final finish (5–10 days) — Backsplash, plumbing trim, appliances, paint touch-up, punch list.

Common causes of delays

  • Material backorders — cabinets, appliances, specialty tile can have 2–8 week lead times. Always order before demo.
  • Unexpected damage — water damage, rot, outdated wiring discovered during demo. Adds 3–7 days.
  • Permit inspections — if inspector finds issues, work stops until corrected (1–3 days).
  • Countertop fabrication delays — single biggest schedule risk. Choose fabricator early.
  • Owner decision delays — if you're picking tile, fixtures, or paint mid-project, that adds days.

How to speed up your remodel

  1. Make all selections before signing contract. Cabinets, counters, tile, paint, fixtures, appliances.
  2. Order materials early. All materials in your garage before demo day 1.
  3. Choose stock or semi-custom cabinets. Custom adds 4-8 weeks vs 1-2 for stock.
  4. Use a fabricator with short lead time. Ask for current "template to install" time.
  5. Avoid layout changes. Same plumbing/electrical locations cuts 3-7 days.
  6. Pick LVP over tile flooring. Faster install, less curing time.
  7. Be available for daily questions. Decisions on the fly mean no waiting on you.

Living through it

  • Set up temp kitchen in dining or living room: microwave, mini-fridge, paper plates.
  • Plan to eat out for at least 2 weeks of the project.
  • Move pantry essentials out before demo day.
  • Protect adjacent rooms with plastic sheeting (we handle this).

Frequently Asked Questions

Can a kitchen remodel be done in 2 weeks?
Only for refresh projects. Anything involving new cabinets and counters needs 3+ weeks because of countertop fabrication time alone.
How much should I budget for a kitchen remodel in The Woodlands?
Mid-range kitchens run $30,000-$60,000. Refreshes can be $5,000-$15,000.
Do you handle the permit process?
Yes. If permits are required (plumbing relocations, electrical upgrades, structural changes), we pull them as part of the project. No markup on permit fees.
Will I have water/electricity during the remodel?
Yes — only the kitchen sink and outlets are out of service. Water and power for the rest of the house stay on.

Have Questions About Your Project?

Free written estimate within 48 hours.

📞 (346) 334-4469
📞 Call Now Free Quote